The contractor says the HDB wall is nonstructural. Can work start before written approval?

Housing category photographHousing

Our renovation contractor says the section of wall we want removed is nonstructural and could be taken down this week. The permit paperwork is still being handled. My partner wants to keep the schedule because our temporary accommodation is costing us money.

This is our HDB flat in Singapore. I have not seen written approval for the proposed wall work. HDB says partial or complete wall demolition and hacking require prior written approval, and owners should not instruct unapproved work.

How do we pause that part of the job and get a reliable revised plan without letting “the paperwork is coming” become permission to start? I want to understand the approved scope and who is responsible for each next step, rather than try to judge the wall myself.

Discussion

5 community replies

Put it in writing that the demolition is not to start before the required written approval is in place. Ask for the application reference, the submitted scope and the eventual approval and conditions. A contractor's description of the wall does not replace HDB's required process.

The HDB guidance also requires contractors from its Directory of Renovation Contractor for renovation work. Verify the contractor and the relevant requirements through HDB. Do not make your decision depend on whether the wall looks thin or sounds hollow.

Ask for a revised schedule distinguishing the wall work from any other work that is properly authorised and can proceed. Then compare the real accommodation and timing costs. Keeping the old end date on paper would not solve a delay in the work needed before it.

I would want your partner involved in the instruction to pause, so the contractor does not receive one message from you and another saying to keep going.

Agree the instruction together and use one written communication route for approvals and schedule changes. Your partner can still challenge the cost and timing of the revised plan. That discussion should happen with the required approval treated as a condition of the wall work.