Should we report our new HDB flat's defects before renovation, even with most of the DLP left?

Housing category photographHousing

Our renovation contractor can start at our new HDB flat next week. We have noticed a few defects since collecting the keys, but my spouse wants to get the work moving and submit one complete list later. He says the Defects Liability Period gives us a year.

The HDB guidance describes a one-year DLP but also asks owners to report items within a month of key collection and before renovation begins. I had not separated the length of the period from the advice about when to report.

We have not started work or submitted our list. Delaying the renovation could disrupt our moving plans, but covering over the areas we want checked does not seem a good way to make the defects easier to resolve.

What should we establish with the Building Service Centre and our contractor before fixing the start date?

Discussion

5 community replies

Your spouse is trying to protect the moving timetable. Make clear that the immediate task is to report what you know and obtain a workable sequence, rather than turn the inspection into an open-ended search for a flawless flat.

If another issue is found after the contractor starts, would the earlier report mean it cannot be added?

Do not treat the first list as proof that every later issue is excluded. Report the new item promptly and ask the BSC to assess it, with the relevant timing and renovation information. You should not decide its cause or coverage yourselves from whether it appeared on the first list.