Our lender accepted the EWS1 form. What building-safety questions remain for us?

Housing category photographHousing

The agent called to say our lender was satisfied with the EWS1 paperwork for a flat we want to buy in England. My partner was relieved and said we could cross fire safety off the list.

I am relieved about the mortgage too, but I do not understand the form well enough to treat it as an answer about the entire building. RICS explains that EWS1 is not a life-safety certificate. We have not yet had the relevant building documents explained to us, including whether any works are proposed or outstanding.

What should we ask the conveyancer and building manager to clarify before we commit? I want to understand both living in the building and any obligations we could be taking on, without assuming that a lending decision answers every safety or cost question.

Discussion

5 community replies

Ask what the specific form says, what it covers and who has reviewed it for your purchase. The RICS explanation concerns the external-wall assessment process and expressly distinguishes it from a life-safety certificate. Do not turn 'the lender accepted it' into a statement about every part of the building.

Ask the building manager for the current relevant fire-safety information and the status of any recommended or planned work. If you do not understand a technical document, get suitable professional help interpreting it. Neither a missing explanation nor an unfamiliar acronym lets you infer the building is safe or unsafe.

Have your conveyancer assess the documents about costs and responsibility for works, including anything outstanding or disputed. Keep that assessment separate from a specialist's advice about physical safety. You need clear answers to both, and neither should be reconstructed from the agent's summary.

I would ask for promised works to be described with their actual status: proposed, commissioned, under way or completed. 'Being sorted' could mean any of those things.

Request the supporting documents and ask what remains uncertain about funding, scope or timing. If a completion date is only an estimate, keep it labelled that way in your decision. A promise to send information later is still an unanswered question at the point you are assessing the purchase.