The landlord sent us last week's Electrical Installation Condition Report and highlighted the date for the next periodic inspection. In another part of the report, an item is marked C2 and the overall result is unsatisfactory.

We rent privately in England. When I asked about the finding, he said the new report meant the electrics had been checked for another five years. I do not know whether an electrician has already been asked to return, or whether any remedial work has happened since the inspection.

[The government's electrical-safety guidance says C2 findings require remedial work, with required work generally completed within 28 days or any shorter period specified in the report](https://www.gov.uk/government/publications/electrical-safety-standards-in-the-private-and-social-rented-sectors-guidance/electrical-safety-standards-in-the-private-and-social-rented-sectors-guidance). That seems to concern a different deadline from the next routine test.

What should we ask for now, including advice about using the affected installation while it is being resolved? I want the finding understood and dealt with, rather than try to judge wiring from the report myself.

Discussion

5 community replies

Ask promptly whether remedial work has been booked or completed, who is responsible for it and what the qualified person advises in the meantime. Quote the report's actual item and date. A future periodic-inspection date does not answer those questions.

The government guidance also requires written confirmation after remedial work. Ask for the relevant completion documentation with the report, rather than accept “someone has been round” as the whole record.

Keep the request and response together with the complete report. If the landlord continues to treat the inspection date as the answer, ask the council's private housing team to consider the documents. You do not need to turn yourself into the person deciding which electrical work is required.

I would be wary of calling this a missed deadline already. The inspection was only last week, and there could be a follow-up appointment you have not been told about.

Agreed: the missing information is the remedial plan and any work already completed. Ask for that now, along with any shorter period stated in the report and qualified advice on interim use. You can challenge the five-year explanation without claiming a breach you have not established.

Join the discussion